    During the implementation of a contingency plan , a team member notices that the plan worked only marginally. There were 3 similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following?

    a) A workaround
    b) A project change request
    c) A new risk rating matrix
    d) A risk responsibility chart review

    #1994
    admin
    Keymaster

    The correct answer is B.

    The project management plan can be changed as a result of the actions needed to manage risks.