    Lara, Project Manager, is in the process of risk identification. She identified that there are some conflicts in the team as to how to execute some part of the deliverable. What she would do to mitigate the risk?

    a) Outsource that piece of work
    b) Introduce training on conflict resolution techniques
    c) Insure that piece of work
    d) Remove that piece of work

    #1847
    Gary
    Guest

    The correct answer is B.

    All the choices listed, except choice B, are examples of transference or avoidance.