Home Forums PMP Questions and Answers Discussion Risk Management Question 29

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #3763
    admin
    Keymaster

    All of the following are results of adding to the risk register in the Plan Risk Response process EXCEPT?

    a) You are in control of the project as it progresses with few surprises.
    b) By managing the plan, you are able to avoid some risks while mitigating the effects of others.
    c) The need for workarounds is minimized
    d) The need for contingency reserves is minimized

    #3764
    admin
    Keymaster

    The correct answer is D.

    As more risks are identified, the amount of contingency reserves set aside to cover those risks will increase, not decrease. However, a project on which thorough risk response planning is done is likely to experience fewer unplanned risk events. Those unplanned events would add more cost to the project than would the reserves for identified risks.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Risk Management Concepts: Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.