Home Forums PMP Questions and Answers Discussion Risk Management Question 27

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #3578
    admin
    Keymaster

    A project team is creating a project management plan when management asks them to identify the project risks and some forms of qualitative outputs as soon as possible. What should the project team provide?

    a) Prioritized list of project risks
    b) Risk triggers
    c) Contingency reserves
    d) Probability of achieving the time and cost objectives

    #3579
    admin
    Keymaster

    The correct answer is A.

    This question essentially asks, “What is an output of the Perform Qualitative Risk Analysis process?” Only Choice A meets that criteria. Choices B and C are parts of the Plan Risk Responses process. Choice D occurs during the Perform Quantitative Risk Analysis process.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Risk Management Concepts: Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    #3585
    REUBEN
    Participant

    A

Viewing 3 posts - 1 through 3 (of 3 total)