  • #3347
    admin
    Keymaster

    During the monitor and control risk process, the risk response owner should be?

    a) Identifying which risks she wants to monitor.
    b) Controlling the identification of response strategies
    c) Informing the project manager of any midcourse correction needed
    d) Updating stakeholders of new strategies for mitigating risks

    #3348
    admin
    Keymaster

    The correct answer is C.

    The risk response owner is assigned to carry out responses and must keep the project manager informed of any changes.