    A fire has just destroyed a warehouse that was being constructed as part of a large project you are managing. What would have been the easiest way to ensure that this force majeure would not significantly impact the cost of your project?

    a) Reduce the impact of such risk by transference
    b) Reduce the probability that the event will take place
    c) Accept the risk
    d) Eliminate the threat by not building the warehouse

    #3286
    admin
    Keymaster

    The correct answer is A.

    Transference by contract or insurance is the best answer.