A project manager has assembled the project team, identified 56 risks on the project, determine what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of data used. The team is continuing to move through the risk management process, what has the project manager forgotten to do?
a) Simulation
b) Risk Mitigation
c) Overall risk ranking for the project
d) Involvement of other stakeholders