Home Forums PMP Questions and Answers Discussion Risk Management Question 19

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2491
    admin
    Keymaster

    A project manager has assembled the project team, identified 56 risks on the project, determine what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of data used. The team is continuing to move through the risk management process, what has the project manager forgotten to do?

    a) Simulation
    b) Risk Mitigation
    c) Overall risk ranking for the project
    d) Involvement of other stakeholders

    #2492
    admin
    Keymaster

    The correct answer is D.

    The process they have used so far is fine, except the input of other stakeholders is needed in order to identify more risks.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Risk Management Concepts: Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.