A project manager is working on a major new product development project when a risk occurs that does not have a risk response plan. What should the project manager do?
a) Hold a risk reassessment and plan a workaround
b) Inform management and communicate the new risk to the team
c) Communicate the planned response to the stakeholders
d) Use some of the reserves to accommodate the risks