    A project manager is working on a major new product development project when a risk occurs that does not have a risk response plan. What should the project manager do?

    a) Hold a risk reassessment and plan a workaround
    b) Inform management and communicate the new risk to the team
    c) Communicate the planned response to the stakeholders
    d) Use some of the reserves to accommodate the risks

    #2446
    admin
    Keymaster

    The correct answer is A.

    The first choice would be to review the risk. Reserves may or may not be used, as in choice D.