    When planning risk responses, the strategy of changing the project management plan to eliminate the risk is known as?

    a) Avoidance
    b) Transference
    c) Mitigation
    d) Acceptance

    #2427
    admin
    Keymaster

    The correct answer is A.

    This is the definition of the risk response strategy of avoidance.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Risk Management Concepts: Project Risk Management