Home › Forums › PMP Questions and Answers Discussion › Risk Management Question 16 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 21, 2019 at 4:45 AM #2426 adminKeymaster When planning risk responses, the strategy of changing the project management plan to eliminate the risk is known as? a) Avoidance b) Transference c) Mitigation d) Acceptance October 21, 2019 at 4:47 AM #2427 adminKeymaster The correct answer is A. This is the definition of the risk response strategy of avoidance. Pass PMP in the First Attempt : PMP Strategy Revise Risk Management Concepts: Project Risk Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In