    Which of the following is the BEST way to describe the outputs of the risk identify process?

    a) A list of risks
    b) A list of triggers
    c) A list of the risk response owners
    d) An understanding of the project risks

    #2383
    admin
    Keymaster

    The correct answer is D.

    The outputs of this step are certainly a list of risks (choice A) and triggers (choice B). Risk response owners (choice C) are determined in Plan Risk Responses. However, it is an understanding of the risks that is important to be able to qualify and/or quantify them and to plan for them.