    A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by a response. Which of the following is the BEST thing for the project manager to do?

    a) Document the new risks and continue the Plan Risk Response Process
    b) Make sure the project work is better understood
    c) Spend more time making sure the risks responses are clearly defined
    d) Get more people involved in the Identify Risks process since the risks have been missed

    #2303
    admin
    Keymaster

    The correct answer is A.

    Did you realize this question describes secondary risks? Identifying secondary risks is good and expected while completing the Plan Risk Responses process. With that in mind, the best thing to do is choice A.

    Revise Risk Management Concepts: Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.