Home Forums PMP Questions and Answers Discussion Risk Management Question 11

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2271
    admin
    Keymaster

    A project manager asked various stakeholders to determine the probability and impact of the no. of risks. He then analyzed assumptions, he is about to move to the next step of risk management. Based on this information, what has the project manager forgotten to do?

    a) Evaluate trends in risk analysis
    b) Identify triggers
    c) Provide a standardized risk rating matrix
    d) Create a fallback plan

    #2272
    admin
    Keymaster

    The correct answer is C.

    This is the Perform Qualitative Risk Analysis process. Only activity which is left out is the probability and impact matrix development.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.