The correct answer is D.
Would you select a choice that said “remove the resource,” like choice A? Why? There is no need for the project manager to take such drastic action, because he would have accounted for the team member’s level of experience and productivity in the project management plan. Since training for project work is the cost of the project, choice B cannot be right. Choice C is not correct, as no impact to the project is referenced in the question. Mentoring (choice D) is the only logical choice, and work that a project manager may be frequently called on to perform.