    While staffing a project in another country, the project leader from that country comes to you with a suggested team consisting of members of the project leader’s family. Your first course of action should be to?

    a) Inquire if hiring only through family lines is common practice in the project leader’s country.
    b) Review the resumes of the individuals to see if they are qualified
    c) Ask the project leader to provide additional names of people unrelated to him/ her.
    d) Use a different project leader to prevent problems later in the project

    #2191
    admin
    Keymaster

    The correct answer is A.

    First action would be to find out whether working with family members is a common practice in that country (choice A), as there is nothing inherently illegal in this activity. Then, you would review qualifications (choice B). Choices C and D may not be necessary after choices A and B are done.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.