A new testing centre is going to be constructed over the next two years. The project sponsor and the project manager have been identified and high estimates begun, it is expected that the project can be completed within budget and on schedule. The onlydifficulty is in acquiring the no. of resources with the correct expertise to complete the work. Under these circumstances, the project manager should spend more time in creating a :
a) Risk Analysis
b) Responsibility Assignment Matrix
c) Responsibility Chart
d) Resource Limited Schedule