Home Forums PMP Questions and Answers Discussion Resource Management Question 4

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #1832
    Gary
    Guest

    A new testing centre is going to be constructed over the next two years. The project sponsor and the project manager have been identified and high estimates begun, it is expected that the project can be completed within budget and on schedule. The onlydifficulty is in acquiring the no. of resources with the correct expertise to complete the work. Under these circumstances, the project manager should spend more time in creating a :

    a) Risk Analysis
    b) Responsibility Assignment Matrix
    c) Responsibility Chart
    d) Resource Limited Schedule

    #1833
    Gary
    Guest

    The correct answer is D.

    A risk analysis (choice A) may help, but not as much as a resource-limited schedule (choice D). A responsibility assignment matrix (choice B) shows who is responsible for what, as does a responsibility chart (choice C). They will not help you manage the project with limited resources. Only D will help meet the defined need.

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.