    A project team member has just completed work on the some part for the new system performance monitor and is now finished with the project. The project manager should?

    a) Evaluate the project’s resource requirements
    b) Provide input to the team member’s performance appraisal
    c) Reevaluate the activity duration estimates
    d) Change the staffing management plan

    #3293
    admin
    Keymaster

    The correct answer is B.

    After a team member completes project work, it is the project manager’s job to provide input to the team member’s manager regarding performance appraisals.