    A project manager says to the team member, “if you cannot complete this activity according to the quality standards you set in place, I’ll remove you from the team that is going to Venezuela for a milestone party with the customer. What form of power is the project manager using?

    a) Reward power
    b) Formal power
    c) Penalty power
    d) Referent power

    #3272
    admin
    Keymaster

    The correct answer is C.

    Penalty power refers to removing some benefit.