    A project team has been arguing for days about the correct way to complete a high level design. This argument has caused a schedule performance index (SPI) to fall to 0.89 and the Cost Performance Index (CPI) to 0.8. if the project manager tells the team, “we will schedule this discussion for our team meeting next week”, the project manager is?

    a) Using earned value
    b) Compromising
    c) Increasing costs even further
    d) Withdrawing

    #2546
    admin
    Keymaster

    The correct answer is D.

    This is an example of conflict and a choice of conflict resolution techniques. The project manager is withdrawing.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Resource Management Concepts: Project Resource Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.