A resource assigned to your project contacts you, trying to get off the team. He knows that an important project in his department is going to be approved and will take place at the same time as yours. He wants to work on the other project. Under these circumstances, what is the BEST thing to do?
a) Keep him if he is a valuable resource
b) Talk to the functional manager about releasing him from the team
c) Release him after he finds a suitable replacement
d) Wait until the last minute to see if the other project is approved