During the first half of the project, 5 team members left for other projects without being replaced , two team members went on vacation without informing you and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a________ for second half of the project.
a) WBS
b) Resource Histogram
c) Staffing management plan
d) Responsibility assignment matrix