    The acceptable range of the variation of a process is the ____ on a control chart.

    a) Mean
    b) Specification limit
    c) Rule of seven
    d) Upper and lower control limit

    #3690
    admin
    Keymaster

    The correct answer is D.

    The control limits are set based on the company’s quality standard and indicate the acceptable range.