Home › Forums › PMP Questions and Answers Discussion › Quality Management Question 23 This topic has 1 reply, 1 voice, and was last updated 5 years, 3 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts January 9, 2020 at 1:18 PM #3327 adminKeymaster A control chart helps the project manager? a) Focus on the most critical issue to improve quality b) Focus on stimulating thinking c) Explore a desired future outcome d) Determine if the process is functioning within set limits January 9, 2020 at 1:20 PM #3328 adminKeymaster The correct answer is D. Choice A relates to Pareto charts. Choices B and C relate to fishbone diagrams. Only choice D relates to control charts. Pass PMP in the First Attempt : PMP Strategy Revise Quality Management Concepts: Project Quality Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In