    A control chart helps the project manager?

    a) Focus on the most critical issue to improve quality
    b) Focus on stimulating thinking
    c) Explore a desired future outcome
    d) Determine if the process is functioning within set limits

    #3328
    admin
    Keymaster

    The correct answer is D.

    Choice A relates to Pareto charts. Choices B and C relate to fishbone diagrams. Only choice D relates to control charts.