Home › Forums › PMP Questions and Answers Discussion › Quality Management Question 21 This topic has 1 reply, 1 voice, and was last updated 5 years, 4 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts December 21, 2019 at 4:26 AM #3276 adminKeymaster All of the following are examples of Control Quality EXCEPT? a) Inspection b) Cost of quality c) Pareto chart d) Fishbone diagram December 21, 2019 at 4:28 AM #3277 adminKeymaster The correct answer is B. Choices A, C, and D are done as part of Control Quality (depending on how they are used). This leaves only choice B, which must be the best answer. Cost of quality is part of Plan Quality. Pass PMP in the First Attempt : PMP Strategy Revise Quality Management Concepts: Project Quality Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In