    The code development phase of a s/w project is nearly complete when the first code review is conducted. During the review, it is discovered that the application is missing functionality required to complete a key business process. However, the product scope never specified its functionality. What should the project manager do?

    a) Reject the functionality as out of project’s scope
    b) Agree to include the functionality in the current phase
    c) Agree to include the functionality in the next release
    d) Assess the impact on the project of including the functionality and inform the sponsor

    #3153
    admin
    Keymaster

    The correct answer is D.

    A project manager must always evaluate the situation before recommending a corrective action or a change.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Quality Management Concepts: Project Quality Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.