    admin
    Keymaster

    The testing results for new computer modulation project have arrived from the seller. The results indicate the project is not meeting the overall quality requirements. If the project manager meets with the team members to analyze the situation, the project manager is involved in which process?

    a) Quality check
    b) Manage quality
    c) Plan quality management
    d) Control quality

    #2584
    admin
    Keymaster

    The correct answer is B.

    The key word here is “overall.” Control Quality (choice D) is incorrect because we are not addressing the specific work performance. Manage Quality process is used to make sure standards and processes were followed.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Quality Management Concepts: Project Quality Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.