    Another project has had a major defect. A project manager has gotten his project team and
    the process engineers involved in analyzing how this might affect their project. Which of the
    following would BEST describe what the group is involved in?

    a) Quality Analysis
    b) Plan quality management
    c) Manage quality
    d) Control quality

    #2512
    admin
    Keymaster

    The correct answer is B.

    The group is using organizational process assets to improve their project. Although the incident just occurred, it was on another project. They are in the Plan Quality process.