    A project manager is identifying the quality standards relevant to the project and determining how to meet them. This activity is a part of which quality process?

    a) Quality Management
    b) Manage Quality
    c) Plan Quality Management
    d) Control Quality

    #2479
    admin
    Keymaster

    The correct answer is C.

    The key words here are “identifying the quality standards” which is done in the Plan Quality Management process.