    A project team has invited many of the project stakeholders to help them inspect quality on the project. Which of the following would NOT be an output of this activity?

    a) Quality management plan
    b) Quality control measurements
    c) Recommended preventive actions
    d) Validated deliverables

    #2436
    admin
    Keymaster

    The correct answer is A.

    Only a quality management plan is not an output of Control Quality.