    A project is facing a major change to the project deliverables. If the project manager is involved in determining which quality standards are relevant to the change, the project manager must be involved in?

    a) Quality Management
    b) Manage Quality
    c) Plan Quality
    d) Perform quality control

    #2392
    admin
    Keymaster

    The correct answer is C.

    Although quality planning usually occurs during project planning, sometimes we need to go back to planning from other processes to make a decision.