During the completion of the project work, the project manager wants to ensure that the quality of the end product is acceptable. The BEST way to do this is by?
a) Checking quality against the standards set in the quality management plan
b) Identifying the quality standards you want the end product to meet.
c) Performing cost benefit analysis
d) Determining the root cause of the problem using a fishbone diagram.
Did you notice the situation is occuring during completion of project work? Choices B and C occur earlier. Choice D does not deal with the quality of the end product of the project, it deals with quality problems that arise.