    The first phase of your project has come to an end. What should you ensure is done BEFORE beginning the next phase?

    a) Verify that resources are available for the nest phase.
    b) Check the project’s progress compares to its baselines
    c) Confirm that the phase has reached its objectives, and have its deliverables formally accepted.
    d) Recommend corrective action to bring the project results in line with project expectation.

    #2230
    admin
    Keymaster

    The correct answer is C.

    A phase or project must be formally closed and accepted.