    A project manager does not have much time to spend on planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. Which of the following would you recommend?

    a) Make sure you have a signed project charter and then start the WBS
    b) Create an activity list before creating a network diagram
    c) Document all the known risks before documenting the High Level Assumptions
    d) Finalize the quality management plan before you determine quality metrics

    #1870
    Gary
    Guest

    The correct answer is B.

    This question is asking which of the choices is the most effective way to move through the planning process. Choice A skips the important steps of defining the scope and other activities. High-level assumptions are determined prior to risk identification in the planning processes, making choice C incorrect. Metrics are part of the quality management plan, making choice D incorrect. Choice B is best, as the activity list is created immediately before the network diagram.