    Your project is managed in a Projectized Organization. It has just entered the close project process. Under the circumstances, which of the following should be of your greatest concern?

    a) Setting yourself up to take over a large multi year project.
    b) The team is not focused on completing the project.
    c) You will have extra pressure from the customer.
    d) Making sure your manager knows that the project is almost completed.

    #2375
    admin
    Keymaster

    The correct answer is B.

    Because you are in a projectized organization, the team will either be looking for new jobs or trying to extend the length of the project so they have work for a longer period of time.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.