The WBS and the WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsibility matrix be issued. The project has a budget of US$100,000 and is taking place in 3 countries using 14 human resources. There is little risk expected for the project and the project manager has managed many projects similar to this one. What is the next thing to do?
Complete risk management and issue the responsibility assignment matrix
Make sure the project scope is defined
Understand the experience of the sponsor on similar projects
Create an activity list