    A seller is awarded a contract to build a pipeline. The contract terms and conditions require a work plan be issued for the buyer’s approval prior to commencing work, but the seller fails to provide one. Which is the BEST thing for the buyer’s project manager to do?

    a) File a letter of intent
    b) Develop the work plan and issue it to the seller to move things along
    c) Issue a default letter
    d) Issue a stop work order to the seller until a work plan is prepared

    #3333
    admin
    Keymaster

    The correct answer is C.

    Any time that a seller does not perform according to the contract, the project manager must take action. The preferred choice might be to contact the seller and ask what is going on, but that choice is not available here. Therefore, the best choice is to let him know he is in default (choice C).

    Pass PMP in the First Attempt : PMP Strategy

    Revise Procurement Management Concepts: Project Procurement Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.