Home Forums PMP Questions and Answers Discussion Procurement Management Question 17

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2648
    admin
    Keymaster

    The project manager is asked to assist the procurement manager in giving some sellers a tour of the facilities where the project work will be done. What part of the project management process they are in?

    a) Initiating
    b) Planning
    c) Executing
    d) Monitoring and controlling

    #2649
    admin
    Keymaster

    The correct answer is C.

    Such a tour is part of the procurement process called Conduct Procurements. Conduct Procurements occurs during project executing.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Procurement Management Concepts: Project Procurement Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)