    During completion of the project, you notice that a deliverable, integral to the project has not been received. The seller says that the work is not part of the contract. You remember discussing it during negotiations and even coming to agreement, but you cannot find it in the contract. Which of the following BEST describes this situation?

    a) The deliverables may be described in the specifications and not in the contract
    b) The deliverable is required to be completed
    c) A change to the contract is required in order to get the deliverable
    d) The seller is required to complete the deliverable

    #2482
    admin
    Keymaster

    The correct answer is C.

    If it is not in the contract (which includes the specifications), a change order is needed to acquire it.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Procurement Management Concepts: Project Procurement Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.