    When entering into procurement, it is best to assume that there will be disputes about the performance of the work as specified, and to?

    a) Include a procedure in the contract describing the means of dispute resolution
    b) Track claims to ensure the best position during litigation
    c) Make sure disputes are never brought to public knowledge
    d) Include a change order provision in the contract

    #2419
    admin
    Keymaster

    The correct answer is A.

    There are certain basic things that should go into all contracts; an arbitration (or dispute resolution) clause is one of them.