Which of the following best describes the project manager’s role during the procurement process?
a) The project manager has only minor involvement
b) The project manager should be the negotiator
c) The project manager should supply an understanding of the risks of the project
d) The project manager should tell the procurement manager how the procurement process should be handled.
As the project manager, you know what the project risks are. You need to make sure that provisions are included in the contract to address these risks.