    You are the seller to develop the project needed for your client’s new product. The project work is underway when you discover that the client is going to make a major change. This change will dramatically change the s/w requirements. What is the BEST thing to do?

    a) Stop work on the software and await instructions
    b) Inform the client of the impact on the project of making such a change.
    c) Ask the client when the change will be finalized and manage the project accordingly
    d) Stop works on part of the project that will not change

    #2370
    admin
    Keymaster

    The correct answer is B.

    Sellers are generally required under contract to keep working unless told otherwise. This rule makes choice B the best choice.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.