You are the seller to develop the project needed for your client’s new product. The project work is underway when you discover that the client is going to make a major change. This change will dramatically change the s/w requirements. What is the BEST thing to do?
a) Stop work on the software and await instructions
b) Inform the client of the impact on the project of making such a change.
c) Ask the client when the change will be finalized and manage the project accordingly
d) Stop works on part of the project that will not change