    Which of the following statement is false?

    a. In Agile, risk is high at the startimg but decreases at faster rate as compared to traditional waterfall approach.
    b. In Agile, most of the time, visibility of the project progress is more as compared to traditional waterfall approach.
    c. In Agile, flexibility to accomodate change is more than traditional waterfall approach.
    d. In Agile, business value reaches customer later as compared to traditional waterfall approach.

    #6771
    admin
    Keymaster

    Correct answer is D.

    In Agile, higher business value items are delivered to the customers through prirotized product backlog and small iterative & incremental cycles.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    30 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.