    You have just been assigned as a project manager for a sizeable engineering project, and you want to quickly review the project’s procedures for managing risks. Which would be the MOST helpful I finding this information?

    a) A risk identification plan
    b) A risk management plan
    c) Environmental process assets
    d) A risk impact matrix

    #4012
    admin
    Keymaster

    The correct answer is B.

    The risk management plan (choice B) identifies how risks will be managed on the project.