    Organization XYZ has been doing its projects through Scrum. After sprint 4, product owner left the company. New product owner joined the project in sprint 5. He requested for few changes in the user stories prioritization. As a scrum master what will you do?

    a. Allow the product owner to make the changes
    b. Guide him that prioritization was done by previous product owner and cannot be changed
    c. Excalate the matter to higher management
    d. Ask the team to continue working on previous priorities.

    #6566
    admin
    Keymaster

    Correct answer is A.

    Product Owner is responsible for the prioritization of the user stories. He ensures that highest value deliverables reach customers as early as possible.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    30 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.