Peter is performing an audit of the projects executed by Organization ABC. He found that in one of the projects, Mary (project manager) does not consider the network diagram as part of Identify risk process. What information she might had missed?
a) Few activities
b) Activity Network details
c) Few Stakeholders
d) Activities converging at or diverging from any activity
In the network diagram when many activities converge to single activity or diverge from single activity then risk increases if that activity is not properly managed and completed.