    Peter is performing an audit of the projects executed by Organization ABC. He found that in one of the projects, Mary (project manager) does not consider the network diagram as part of Identify risk process. What information she might had missed?

    a) Few activities
    b) Activity Network details
    c) Few Stakeholders
    d) Activities converging at or diverging from any activity

    #6553
    admin
    Keymaster

    Correct answer is D.

    In the network diagram when many activities converge to single activity or diverge from single activity then risk increases if that activity is not properly managed and completed.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    30 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.