    One of the stakeholders on the project charter contacts the project manager to discuss some additional scope he would like to add to the project. The project manager asks for details in writing and then works through the Control Scope process. What should the project manager do NEXT when the evaluation of the requested scope is complete?

    a) Ask the stakeholder if there are any more changes expected.
    b) Complete Integrated Change Control
    c) Make sure the impact of the change is understood by the stakeholder.
    d) Find out the root cause of why the scope was not discovered during project planning

    #4008
    admin
    Keymaster

    The correct answer is B.

    Notice that there are many things the project manager could do listed in the choices. The question asks what is the BEST thing to do NEXT. Though they are great things to do, choices A, C, and D are not next. Management of the change is not complete when the Control Scope process is completed. It is important to look at the impact of the change on other parts of the project such as time and cost. Therefore, choice B is the best thing to do next, probably followed by C and then D and A.

    Pass PMP in the First Attempt : PMP Strategy