Home › Forums › PMP Questions and Answers Discussion › PMP Question 70 This topic has 1 reply, 1 voice, and was last updated 4 years, 11 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts June 1, 2020 at 11:38 AM #6296 adminKeymaster Team A is averaging 50 storypoints per three weeks iteration. 200 points worth of functionality is left. How many weeks would be required to complete the development work? A. 0.25 B. 3 C. 4 D. 12 June 1, 2020 at 11:43 AM #6298 adminKeymaster Correct answer is D. Number of iterations required = 200 / 50 = 4 Number of weeks required = number of iterations * iteration duration = 4*3 = 12 Pass PMP in the First Attempt : PMP Strategy All PMP Question & Answers: Question & Answers Revise PMP Concepts: PMP Concepts PMP Tips & Tricks: PMP Tips & Tricks Quiz: 20 Questions Challenge 50 Questions Challenge PMP Agile based Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In