✅ Correct Answer: B. Agree together on a single estimation method
🔍 Explanation:
A. Choose story points since Scrum mandates it
❌ Scrum never mandates story points.
B. Agree together on a single estimation method
✅ Correct – The team must decide a shared approach that works for them.
C. Let the Product Owner decide the estimation style
❌ Estimation is the team’s responsibility, not the Product Owner’s.
D. Skip estimation and assign work in sprint planning
❌ Skipping estimation reduces forecasting and predictability.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram