✅ Correct Answer: B. Clarify the meaning of the burnup chart and how to interpret it
🔍 Explanation:
A. Ask each team to create and use their own burnup chart
❌ Would reduce alignment across teams and create inconsistent metrics.
B. Clarify the meaning of the burnup chart and how to interpret it
✅ Correct – Misinterpretation is causing confusion; the first step is to ensure everyone understands what the chart shows before making process changes.
C. Freeze the scope immediately to prevent further confusion
❌ Scope freeze is a drastic step that doesn’t address the root cause of misunderstanding.
D. Increase the frequency of progress reporting across teams
❌ More frequent reporting won’t help if the metric itself is misunderstood.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram