PMP Question 663

Home Forums PMP Questions and Answers Discussion PMP Question 663

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28551
    admin
    Keymaster

    During a review, stakeholders see the burnup chart’s “scope line” rising and assume the team is intentionally adding work and delaying delivery. The Product Owner is concerned about the misunderstanding.

    What should the Scrum Master do next?

    A. Explain that scope growth is tracked, not caused, by team
    B. Limit scope changes during sprint to protect delivery date
    C. Replace burnup with burndown to avoid scope confusion
    D. Ask team to hide scope line till after sprint review

    #28552
    admin
    Keymaster

    ✅ Correct Answer: A. Explain that scope growth is tracked, not caused, by team

    🔍 Explanation:
    A. Explain that scope growth is tracked, not caused, by team
    ✅ Correct – Burnup charts visualize scope changes, helping transparency. Stakeholders need context to interpret it correctly.

    B. Limit scope changes during sprint to protect delivery date
    ❌ May be necessary sometimes, but limits agility and feedback loops.

    C. Replace burnup with burndown to avoid scope confusion
    ❌ Hides valuable info. Burnup is more transparent in scope change cases.

    D. Ask team to hide scope line till after sprint review
    ❌ Violates Agile value of transparency, misleads stakeholders.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    4 Situational based Practice Tests : Agile Test Series

    PMP/Agile Useful Resources : PMP/Agile Resources

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area & Agile based Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.