✅ Correct Answer: A. Switch to a burnup chart to reflect scope adjustments
🔍 Explanation:
A. Switch to a burnup chart to reflect scope adjustments
✅ Correct – Burnup charts separate work done from scope changes, giving clearer visibility when scope increases mid-sprint.
B. Update burndown chart only at sprint end
❌ Misleads the team during the sprint, negating transparency.
C. Use cumulative flow diagram to track effort
❌ Useful for Kanban or flow tracking, but not for scope vs. progress clarity.
D. Break tasks smaller to smooth the burndown line
❌ May help chart smoothness but doesn’t address scope changes.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 Situational based Practice Tests : Agile Test Series
PMP/Agile Useful Resources : PMP/Agile Resources
Pass PMP in the First Attempt : PMP Strategy
All PMP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP Concepts
PMP Tips & Tricks: PMP Tips & Tricks
PMP Knowledge Area & Agile based Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram